Urban Wastewater Treatment Plant
This urban wastewater treatment plant is located in Kazakhstan, Center Enamel provided and installed 2 sets of Glass-Fused-to-Steel tanks for this plant on 2013, the two GFS tanks are with enamel roof and handrails, and we sent 2 installation consults to help with the tank installation.
Location | Kazakhstan |
Tank Model | Ø17.05m*15.6m |
Quantity | 2 sets of GFS tanks |
Tank roof | enamel roof |
Tank color | forest green |
Tank coating | 2 enameling 2 firing |
Installation | 7 people, 50 days |
Installation Date | June, 2013 |